Minimbah Court - Banks Street Social Housing - Fact Sheet

13 May 2026

The Minimbah Court 1950’s social housing complex at Solander Place, Banks Street, is being redeveloped from 12 units to 30 units.  Residents wished to provide input to inform a good outcome prior to the plans being submitted but this was precluded and thus the only avenue available was ACAT. Recent media suggests that residents’ ACAT appeal resulted in a major delay to the project of 2 years.  The timeframes detailed in the FACT SHEET show:

  • Time from Minimbah Court being vacated by tenants to the redevelopment DA being lodged is 4 years (2020 to 2024).
  • Time from ACAT application for review of DA Decision being lodged to ACAT decision in favour of the development proposal is 5 months (28 November 2024 to 3 April 2025).
  • Time after ACAT Decision on DA to commencement of works at Minimbah Court site was 12 months (3 April 2025 to 26 March 2026).

Minimbah Court Social Housing Redevelopment Fact Sheet